2016 Micro-Surfacing Project

​Work Timeline:


July 27th Micro-Surfacing will begin and run through Aug. 3rd.

Please review letters to residents from the contractor for this project here

See locations for Micro-Surfacing in links here

See City letter for Residents here

Project Description:



The work will be completed per the contract documents which are attached via links below.  The following tasks will be completed per this project:
  • Crack filling all cracks
  • Spray patching all alligator cracks and pot holed areas
  • Minor patching repair or asphalt replacement as needed
  • Mill & overlay on Frost Woods Road, three sections
  • Application of Micro Surfacing on various streets
  • Pavement marking on various streets